May 2021  

First stage of detailed investigations begin: Wall Paintings Conservator, Dr Andrea Kirkham, removes small areas of whitewash to check for traces of wall paintings - none are revealed.  The remaining loose plaster on the Nave wall is removed and secured.  Drake's Tomb is given temporary protection in case of plaster fragments falling in the North Aisle. The church can re-open after deep cleaning timed for the relaxation of Covid regulations around 21 June.

2021.05.11a sm Investigations wall painting plaster.A Kirkham.R Blackman.Photo A Rae

    Result of our Expression of Interest to the NLHF: we are recommended to re-submit basing our project on the repairs needed to remove St Peter's from the 'Heritage at Risk Register' and including work to extend peoples understanding of the importance and value of the church and it's nature-rich churchyard. Plans for a kitchen & toilets to create a community hub will need to wait for a second phase.
     
April 2021   Initial survey for the presence of bats will be followed by detailed surveys once they are out of hibernation.
     
March 2021   Expression of Interest submitted to the National Lottery Heritage Fund for a grant of £850,000. We will need to raise the other £100,000 ouselves.
     
January 2021   Wonderful news! We have recieved a £24,000 grant from the Government's Culture Recovery Fund.  This will go a long way to paying for the specialist investigations we need.
     
December 2020   Plaster fragments from the damaged wall are being examined by a conservation specialist to see if there are any traces of wall paintings hidden by the layers of whitewash
    Repairs to the plaster work delayed by the need to fund-raise to cover the costs and further Covid lockdowns preventing access.
    The church remains closed.
     
October 2020   Headly Trust awards a grant of £3,500 towards weather-proofing repairs
    Facebook and Just Giving campaigns go live!
     
August 2020   Application made to Heritage England ‘Covid-19 Heritage at Risk Emergency Fund’ for £24,000, decision expected soon.
    A bat survey in the churchyard identifies 7 bat species using the space.
     
June 2020   Church remains closed until plasterwork can be assessed and stabilized and Covid 19 restrictions eased
    NLHF Grant Expression of Interest delayed due to NLHF giving priority to Corona virus related emergency projects
    Enabling Works identified; Project Architect received quotes from specialists and experts for the investigative stage of the project
     
May 2020   Planning continues with Project Schedule, grant applications and developing a publicity campaign despite Corona Virus lockdown
     
March 2020   Application made to the Headley Trust for £7,000.  Decision expected October
    Church closed and all fund-raising events postponed due to Corona Virus
    Project Architect appointed: Ruth Blackman of Birdsall, Swash and Blackman Ltd
     
February 2020   Large area of plaster falls off the inside of the nave wall; church closed awaiting analysis and stabilisation.
     
January 2020   Diocesan Advisory Committee team visit St Peter’s to discuss proposed works and contractor access
     
December 2019   Essential work to deal with worst penetration by rain water is completed.
     
November 2019   Norfolk Churches Trust awards grant of £1,000 for urgent repairs
     
 October 2019   Friends of St Peter’s Church is inaugurated.
£1,125 raised as a result of the first meeting